Parcel Maps in Sausalito, CA

We prepare parcel maps, lot line adjustments, and SB 9 urban lot splits in Sausalito, Marin County, from the retracement of 1870s-era subdivision lines through the traverse and closure the city requires.

Parcel Maps in Sausalito: Local Conditions

Sausalito's subdivision ordinance is old, specific, and still binding. SMC section 9.20.010 requires that an accurate and complete survey be made of the land to be subdivided, and the sections that follow require a traverse sheet in a form approved by the City Engineer giving latitudes, departures, and coordinates and showing mathematical closure, with the traverse of the exterior boundaries closing within one foot in ten thousand feet of perimeter before balancing. Where the County Surveyor or the City Engineer has established a system of coordinates, the survey must be tied into it, and all monuments, property lines, and the centerlines of streets, alleys, and easements adjoining or within the tract must be tied into the survey. On lots laid out in the 1870s across slopes nobody had walked, meeting that standard is real work.

The dimensional rules constrain the design as much as the terrain does. No parcel may be less than 30 feet wide at any point, average parcel width may not be less than 50 feet — computed as parcel area divided by the length measured down the center of the parcel — and street frontage of at least 30 feet is required on the front parcel line. SB 9 adds its own standards under SMC section 9.70.030, including a plat map drawn to scale by a licensed land surveyor or registered civil or structural engineer, and new flag lots that must have at least 10 feet of street frontage while leaving at least 20 feet to the remaining lot.

We recover controlling monuments, run GNSS and total station control with closure we can defend, scan improvements that bear on the map, and deliver the tentative exhibit, traverse package, and checked map. See Sausalito monument preservation and parcel maps versus tract maps.

Full service details, process, and deliverables: Parcel Maps & Lot Line Adjustments · All surveying in Sausalito: Sausalito land surveying

What's Included

  • Complete Subdivision Map Act compliance
  • Tentative through final map recordation
  • Lot line adjustments and lot mergers
  • City and county surveyor review coordination
  • Scan-based topo included in the same mobilization
  • Boundary resolution by a licensed land surveyor

Our Process

1

Feasibility & Boundary Resolution

We research title, resolve the existing boundary, and confirm your split or adjustment complies with local zoning minimums before you spend on applications.

2

Tentative Parcel Map

We prepare the tentative map and supporting topographic base, and submit through the city or county planning process.

3

Conditions of Approval

After approval, we coordinate the survey-related conditions — monumentation, easements, dedications — alongside your civil engineer where improvements are required.

4

Final Map & Recordation

We prepare the final parcel map, carry it through county surveyor examination, set the required monuments, and record the map with the county recorder.

Parcel Maps in Sausalito: FAQ

SMC Title 9 requires a traverse sheet approved in form by the City Engineer, giving latitudes, departures, and coordinates and showing mathematical closure, with the traverse of the exterior boundaries and of each block closing within one foot in ten thousand feet of perimeter before balancing when computed from field measurements. We run and document the network to meet that, and submit the traverse package with the map.
SB 9 is state law and the city applies objective standards in SMC section 9.70.030 on top of the state eligibility conditions, including flag lot frontage rules and a plat map prepared by a licensed land surveyor or a registered civil or structural engineer. One provision is squarely a survey item: where no setback is required because a structure is rebuilt in the same location and to the same dimensions, verification of size and location requires pre- and post-construction surveys by a California-licensed land surveyor.
The code defines average parcel width as the area of the parcel in square feet divided by the length in feet measured down the center of the parcel, and separately requires no parcel be less than 30 feet wide at any point. On the narrow, angular lots typical here, those two tests can disagree with intuition, which is why we compute them from the surveyed boundary before any design work is committed to.

Need Parcel Maps in Sausalito?

Call (510) 543-2220 or request a quote — we'll scope your Sausalito project and give you a fixed price.

Meeting-first estimates • Response within 24 hours • Serious projects only